2013 03 15

Lithuania's KDS says it will go to European courts over LNG terminal link tender

Kauno Dujotiekio Statyba (Kaunas Pipeline Construction, or KDS), which has built 80 percent of Lithuania's gas pipelines, is set to continue litigation with Klaipėdos Nafta (Klaipėda Oil) over what it says is a poorly organized bidding procedure for a contract to link a planned liquefied natural gas (LNG) terminal to the country's grid, the business daily Verslo Žinios reports.
„Klaipėdos naftos“ bendrovės teritorijoje
„Klaipėdos nafta“ / Aurelijos Kripaitės/15min.lt nuotr.

"We believe that our arguments are strong and that we have a good chance of wining the (court) process. I don't think it'll take long before the court yields to the pressure to lift the current precautionary measures, which have put the entire procurement process on hold," it quoted Henrikas Bartusevičius, the CEO of KDS, as saying.

If Klaipėdos Nafta signs a contract with Germany's PPS Pipeline Systems, the other bidder, KDS will go all the way up to the European Court of Justice, if needed, to seek compensation from the developer of the LNG terminal project for losses due to the poorly-organized tender process, Bartusevičius says.

"In my opinion, our rival - Germany's PPS - has lowered the cost estimate to an unreasonable level. The choice is simple: either a lower risk for the whole project and a higher price, or a higher risk of the project not being implemented, but a lower price," he said.

PPS offered to build the pipeline link for 95 million litas (EUR 27.5m), not including VAT, some 20 million litas lower than KDS' 115-million-litas bid.

KDS was named the winning bidder at the end of last year, but the Public Procurement Office annulled the results of the bidding. Therefore, Klaipėdos Nafta in February invited the bidders to submit new offers, and this time, the likely winner is PPS.

Report mistake

Successfully sent

Thank you

Economy

Lithuanian producers of EPS on the way to circular economy
Gilužio Rivjera by the real estate company Homa – hundreds of apartments and millions in investment
Capitalica fund successfully issued bonds amounting to EUR 5 million to finance the Verde project in Riga

Feature

State Progress Strategy 'Lithuania 2050': will Lithuania become the 'Silicon Valley' of social enterprise?
Citus Experts: Planning to Furbish or Brush Up your Home Interior? Get Ready for a Brutal Run
How do the country's most desirable employers nurture IT talents?

Opinion

Ramūnas Vilpišauskas. The president’s achievements in Brussels were modest
Laurynas Jonavičius. Will the new German government’s foreign policy coincide with Lithuanian interests?
Eastern Partnership ‘beyond westlessness’: a new momentum for the European integration

Politics

Taiwanese Minister Ming-hsin Kung – about Lithuania’s strengths and the two countries’ looming plans
The double standards of “values-based policy”: Lithuania did not join the condemnation of Turkey
Behind the scenes of ambassadorial appointments: Seimas looking for clarification on continuing questioning at the Presidential Palace