The Pomerania wind farm, which is the first Ignitis Groups’ project of its kind in Poland, comprises 29 wind turbines with a nominal capacity of approximately 3–3.3 MW.
“Completion of Pomerania wind farm is another important step towards the decarbonisation of the Poland energy system. It is also exceptionally important to Ignitis Group because it will increase the green generation portfolio of the Group and strengthen the company's position in the growing renewable energy sector of the neighbouring country”, says Darius Maikštėnas, Chairman of the Board and CEO of Ignitis Group.
It is estimated that the Pomerania wind farm will start operating at full capacity (94 MW) beginning from spring of 2021, when the turbine connection to the grid and other unfinished works are complete. The total annual generated electricity will amount to 300 GWh, which will power around 160,000 households every year with clean energy.
Planned investments to the project is estimated at about EUR 127 million.
The green generation development is one of core priorities of sustainability goals of Ignitis Group, which are established in the long-term strategy of the company. Ignitis Group is working to develop green generation capacities with the total operational capacity of 4 GW by 2030. Additionally to Pomerania wind farm in Poland, the Group develops similar projects in Lithuania too. The wind farm project in Mažeikiai region, where 14 wind turbines with the total capacity of up to 63 MW will generate green electricity, is currently under development.